Subject: Resolution
authorizing execution of a LAP Supplemental Agreement with FDOT for the
Leesburg-Wildwood Trail
![]()
Staff Recommendation:
Staff
recommends approval of the resolution authorizing execution of the LAP
Supplemental Agreement for the Leesburg-Wildwood Trail reducing the funding
amount for Construction Engineering and Inspection (CEI) services to
$148,645.00.
Analysis:
This
LAP Supplemental Agreement is a housekeeping issue required by Florida
Department of Transportation (FDOT) reducing the funding amount for CEI
services from the original estimated project amount of $208,395.00 to
$148,645.00, a reduction of $59,750.00.
All
original project funding amounts were based on estimated costs at the time the
grant was approved. Actual construction
and CEI costs were lower than the approved grant funding. FDOT requires all grant funding to be
adjusted to the actual contracted costs.
This supplemental agreement is to reduce the CEI costs based on the
final negotiated contract amount of $148,645.00.
Options:
1. Approve the resolution authorizing execution
of the LAP Supplemental Agreement.
Fiscal Impact:
There
is no fiscal impact to the City related to this Supplemental Agreement. The Leesburg-Wildwood Trail project is 100%
funded by FDOT.
|
Original |
Supp
#1 |
New
Totals |
|
|
Construction |
$ 1,389,298 |
- |
$ 1,389,298 |
|
CEI |
208,395 |
(59,750) |
148,645 |
|
Grant Award |
$ 1,597,693 |
$ (59,750) |
$ 1,537,943 |
|
Department: _Public Works_________ Prepared
by: _Mike Thornton______ Attachments: Yes__X_ No ______ Advertised: ____Not Required __X___ Dates: __________________________ Attorney
Review : Yes___ No ____
_________________________________ Revised 6/10/04 |
Reviewed by: Dept. Head ________ Finance Dept. __________________ Deputy
C.M. ___________________ Submitted
by: City Manager ___________________
|
Account
No. 031-0000-334-7209__ Project
No. _______ __________ WF No. _____065420/15_________ Budget 1,597,693_ ________ Available
__ _ 1,431,574__________ |
RESOLUTION NO._______________
RESOLUTION OF THE CITY COMMISSION OF THE CITY
OF LEESBURG, FLORIDA AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE A
SUPPLEMENT TO AN EXISTING LOCAL AGENCY PARTICIPATION (LAP) AGREEMENT WITH THE
FLORIDA DEPARTMENT OF TRANSPORTATION FOR THE LEESBURG-WILDWOOD MULTI-USE
RECREATIONAL TRAIL; AND PROVIDING AN EFFECTIVE DATE.
WHEREAS,
the State of Florida Department of Transportation and the
City of Leesburg, Florida desire to facilitate the Leesburg Wildwood Trail and,
WHEREAS,
the State of Florida Department of Transportation has requested the City of
Leesburg, Florida to execute and deliver to the State of Florida Department of
Transportation the Supplemental Local Agency Program Agreement for the aforementioned
project, FPN 424444-1-58-01.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF
THE CITY OF LEESBURG, FLORIDA:
THAT the Mayor and City Clerk are hereby
authorized to make, execute, and deliver to the State of Florida Department of
Transportation the Supplemental Local Agency Program Agreement for the
aforementioned project, FPN 424444-1-58-01.
THAT
this resolution shall become effective immediately.
PASSED
AND ADOPTED by the City
Commission of the City of Leesburg, Florida, at a regular meeting held the __14th_
day of __January___ 2013.
__________________________
Mayor
ATTEST:
__________________________________
City Clerk