Description: AGENDAHED.JPG
  

Item No:                    5D.

 

Meeting Date:           June 24, 2013

 

From:                          Mike Thornton, Purchasing Manager for

                                    Al Purvis, Chief Water Plant Operator, Public Works Department

 

Subject:                      Resolution authorizing execution of an agreement with Sanders Company to supply and install well station controller upgrades

 

 


Staff Recommendation:

Staff recommends approval of the execution of a supply and install services agreement with Sanders Company for nine well station upgrades for a total amount of $124,978.00.

 

Analysis:

The City of Leesburg uses a Combination Well Pump Station Control Panel with Supervisory Control and Data Acquisition (SCADA) Remote Telemetry Unit (RTU) to monitor and control the water wells.  All panels contain a SCADA Programmable Logic Controller (PLC) and color touch screen displays.

 

Two sites will receive new combination panels, in their entirety, with new factory tested panels with the following electronic components - PLC, Motor Circuit Protector (MCP) Breaker, Solid State Reduced Voltage (SSRV) starter, pressure transducer, radio, battery backup, antenna, antenna cable and programming/startup.

 

All other sites will receive a replacement PLC complete with the following panel accessories, PLC, Display, replacement I/O, battery backup, antenna, antenna cable and programming/startup.

 

TASK

FACILITY

PHYSICAL LOCATION

Replace PLC

WTP – Leesburg Airport

32733 Echo Drive, 32788

Replace PLC

WTP – Lake Square Mall

10399 U.S. HWY 441, 32788

Replace PLC

Well #9

310 South Palmetto Street, 34748

Replace PLC

Well #14

601 West Dixie Avenue, 34748

Replace PLC

Well #15

1115 West Dixie Avenue, 34748

Replace PLC

Well #16

1302 East Main Street, 34748

Replace PLC

Highland Lakes Well #2

26234 South U.S. HWY 27, FL 34748 

Replace Full Panel

Well #10

515 West Dixie Avenue, 34748

Replace Full Panel

Well #11

1 Dozier Circle, 34748

 

The benefits of this project will be the improvement of the system’s integrity, avoidance of excessive maintenance costs, and reduction of the risk of a system-wide failure causing overflows and spills.

 

The primary reason for replacing the controls and or complete cabinets is because of the age of the equipment.  At wells 10 & 11 a complete upgrade to the starters and controllers which are currently obsolete is being accomplished. The current starters are from the 1960’s and the City has been fortunate to have been able to keep everything running.  Both sites are at and near the Rogers Park area and the Community Building entrance.  These locations are part of the high profile areas which are being considered for different types of future programs.

 

At the remaining sites, the current Siemens D-620I PLC’s are obsolete and new repair parts are no longer available.  Staff has utilized old spare units to keep the existing ones operational.  All of these sites are on the City’s potable wells which are used every day for drinking water and/or fire protection. These sites are critical and need to be functioning at all times, as well as, avoiding compliance issues with numerous regulatory agencies.

 

On April 24, 2013, the Purchasing Division issued Invitation to Bid number 130301. On May 23, 2013, the City received only one bid response.  A responsive and responsible sealed bid was received from the Sanders Company for a total amount of $124,978.00.  It is believed only one bid was received due to the nature of the specialized equipment required by the specifications.  The specifications required specific programmable logic controls manufactured by Sci-Trol (Sanders Company is the licensee for this area) or the Rockwell Company.

 

Water Plant operations staff has advised that based on previous purchases the bid prices provided by Sanders Company appear to be fair and reasonable.  Sanders Company has received prior contract awards for several successful past projects both as a prime contractor and subcontractor and is deemed a responsible contractor.

 

Options:

1.  Approval award of the bid and execution of the agreement with the Sanders Company; or

2.  Such alternative action as the Commission may deem appropriate

 

Fiscal Impact: 

Funds for this project have been specifically budgeted for and are available from the water Renewal and Replacement (R&R) funds.

 

Submission Date and Time:    6/19/2013 6:38 PM____

Department: __Public Works__________

Prepared by: _Terry Pollard_________

Attachments: Yes __X__ No ______

Advertised: __X__ Not Required _____

Dates: April 23, 2013____________

Attorney Review : Yes___ No _X_

 

_________________________________

Revised 6/10/04

 

Reviewed by: Dept. Head ________

 

Finance Dept. _BLM,_____________

 

Deputy C.M. ___________________

Submitted by:

City Manager ___________________

 

Account No. 043-3099-533-6410____

 

Project No. _430003_____________

 

WF No. ____0811126/001________

 

Budget ____$125,000.00_________

 

Available __$125,000.00_________


 

RESOLUTION NO._______________

 

RESOLUTION OF THE CITY COMMISSION OF THE CITY OF LEESBURG, FLORIDA AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE AN AGREEMENT WITH THE SANDERS COMPANY TO FURNISH WELL STATION CONTROL PANEL AND LIFT STATION UPGRADES FOR THE PUBLIC WORKS DEPARTMENT AT NINE  SITES FOR A TOTAL COST OF $124,978.00; AND PROVIDING AN EFFECTIVE DATE.

 

BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF LEESBURG, FLORIDA:

 

            THAT the Mayor and City Clerk are hereby authorized to execute an agreement with SANDERS COMPANY whose address is 2816 SE Monroe Street, Stuart, FL 34997 to furnish well station control panel and lift station upgrades pursuant to Invitation to Bid 130301.

 

             THAT this resolution shall become effective immediately.

 

PASSED AND ADOPTED by the City Commission of the City of Leesburg, Florida, at a regular meeting held the __24th___ day of __June__ 2013.

 

 

 